Road access to a new subdivision between Osage and Upton. Proposed roadway would be approximately 3,900 feet in length and utilize a previously constructed roadway. Project name change from Hartland Subdivision Right-of-Way.
Location
Upton Osage Geographic Area.
Project timeline
1
Scoping Start
03/11/2016
2
Decision
11/2017 (Estimated)
3
Implementation
11/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Use Adjustments; Special Use Authorizations; Road Maintenance; Road Improvements/Construction |
| Special Use Authorization - Use of NFSR 1325.E for Access to Subdivision | Decision Signed Date: 11/20/2017 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T47N R64W Sec 21, 22 |