Removal of existing overhead power line to a building on the Routt National Forest that has previously been removed. All existing power poles will be cut off at 1 foot below grade and the hole filled. Each pole will be removed whole or cut to length.
Location
Mad Creek area of the HPBE RD, Routt National Forest
Project timeline
1
Scoping Start
10/01/2015
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Decision Decided Date | 09/28/2016 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Hahns Peak/Bears Ears Ranger District |
| Legal Land Description | T7N, R85W, Sec 11, 6th PM |