Authorization to Powder River Energy Corp. to upgrade and maintain an existing powerline supply, less than 33-kV, within the right-of-way to supply electricity to an oil well for Petro-Hunt.
Location
Thunder Basin National Grassland
Project timeline
1
Scoping Start
07/05/2016
2
Decision
01/2017 (Estimated)
3
Implementation
01/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Amendment to Special Use Authorization, PRE Corp. 14.4 and 24.9kV | Decision Signed Date: 01/30/2017 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | S11 T43N R71W, 6th P.M. |