Install a headgate, measuring flow box, 991 feet of 24-inch diameter pipe along existing ditch right-of-way. In addition to installation of in-channel diversion and in-stream structures.
Location
Project is located off of National Forest System Road 850.1A.
Project timeline
1
Scoping Start
02/23/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8); 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance; Watershed Improvements |
| Battle Creek Ditch and Stream Enhancement | Decision Signed Date: 08/01/2018 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Brush Creek/Hayden Ranger District |
| Legal Land Description | SW1/4SE1/4 Sec. 30 T. 13 N., R. 87 W., 6th Principal Meridian, Carbon County, Wyoming. |