Drilling one oil well; road construction and reconstruction to access well pad; installation of pipeline and electric utility, and reclamation. Proponent is HD Adams.
Location
Thunder Basin National Grassland - Spring Creek Unit
Project timeline
1
Scoping Start
08/30/2019
2
Decision
05/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (17), 36 Cfr 220.6(E)(17) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations; Minerals Or Geology Plans Of Operations; Natural Gas; Oil; Road Maintenance; Road Improvements/Construction |
| Camp Creek Federal F-3 Oil Well and Associated Uses | Decision Signed Date: 05/07/2020 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | Sec 6 T54N R70W, 6th P.M. |