Realignment of existing power lines to accommodate coal mining operations.
Location
Thunder Basin National Grassland. Adjacent to NARM, east of County Road 4, and generally west of Teckla electrical substation.
Project timeline
1
Scoping Start
10/22/2018
2
Decision
12/2018 (Estimated)
3
Implementation
12/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| 69-kV and 230-kV Power Line Relocations at North Antelope Rochelle Mine | Decision Signed Date: 12/10/2018 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | Sec. 3 T41N R71W; Sec. 34 T42N R71W |