Issuance of mineral material sale contract for use of material at Antelope Mine for an additional 5-year term to begin in 2021. The applicant and proponent is Navajo Transitional Energy Company, LLC. The existing sale contract period ends in 2020.
Location
Vicinity of Antelope Mine. Thunder Basin NG.
Project timeline
1
Scoping Start
08/06/2020
2
Decision
11/2020 (Estimated)
3
Implementation
01/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Mineral Material Contract at Antelope Mine | Decision Signed Date: 11/13/2020 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | Sec. 1, 2, 12 T40N R71W; Sec. 30, 31 T41N R71W |