Description : Union Telephone Company has proposed to install, operate, and maintain new facilities at the Buffalo Pass Communications Site including an 80-foot self-supporting lattice tower, an electronics and generator building, and a propane tank.
Location
Buffalo Pass Communications Site off National Forest System (NFS) Road 310.1A.
Project timeline
1
Scoping Start
07/26/2021
2
Decision
04/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Union Telephone Company New Facility Install-Buffalo Pass Communications Site | Decision Signed Date: 04/05/2022 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Hahns Peak/Bears Ears Ranger District |
| Legal Land Description | Not Applicable |