Installation of buried electrical power lines along National Forest System Road 1258 and spur roads, which are not open to motorized public travel, to serve oil well pads in the Clareton Oil Field.
Location
1 to 2 miles east of County route 7C, Bruce Road. Thunder Basin NG.
Project timeline
1
Scoping Start
08/11/2022
2
Decision
11/2023 (Estimated)
3
Implementation
11/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance; Minerals Or Geology Plans Of Operations |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | Sec. 8 and 9 T42N R65W |