Addition of 220 acres to special use area at NARM. Proponent is Peabody Powder River Mining, LLC.
Location
North Antelope Rochelle Mine
Project timeline
1
Scoping Start
01/05/2023
2
Comment Period
01/05/2023
3
Decision
10/2023 (Estimated)
4
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Special Use Authorization Amendment at North Antelope Rochelle Mine | Decision Signed Date: 10/31/2023 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T41N R69W, T41N R71W, T42N R69W, T42N R70W, T42N R71W |