Right-of-way with oil and gas and water pipelines and buried electric power line installation.
Location
Thunder Basin NG, vicinity of Antelope Flat.
Project timeline
1
Scoping Start
06/09/2023
2
Decision
07/2023 (Estimated)
3
Implementation
07/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations; Minerals Or Geology Plans Of Operations; Natural Gas; Oil |
| Special Use Authorization Pipeline Utility Right-of-Way EOG Resources | Decision Signed Date: 07/18/2023 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | Sec. 20, 21 T41N R72W |