Debenham Energy wishes to install three wind energy testing sites on the Pole Mountain unit of the Laramie District. Initial activities would consist of installing up to three Meteorlogical Towers and one LIDar unit.
Location
Pole Mountain area of the Medicine Bow/Routt National Forest
Project timeline
1
Scoping Start
04/2024 (Estimated)
2
Decision
07/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Laramie Ranger District |
| Legal Land Description | Not Applicable |