Replacement of the Sunshine Express lift, development of a new snowmaking control pumphouse and associated infrastructure, and construction of the Thunderhead Hiking Trail Cutoff.
Location
Steamboat Springs Ski Resort
Project timeline
1
Scoping Start
08/01/2024
2
Decision
03/2025 (Estimated)
3
Implementation
03/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Steamboat Ski Resort Sunshine Lift Replacement | Decision Signed Date: 03/18/2025 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Hahns Peak/Bears Ears Ranger District |
| Legal Land Description | Not Applicable |