construct 4 miles of trails in order to enhance public access and recreational opportunities on the Pine Ridge Ranger District.
Location
T31N, R51W, Sections 24,25,26; T31N, R50W, Section35
Project timeline
1
Scoping Start
06/03/2019
2
Decision
10/2019 (Estimated)
3
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Great Plains Trail Additions | Decision Signed Date: 10/22/2019 |
| Forests | Nebraska National Forest |
| Districts | Pine Ridge Ranger District |
| Legal Land Description | Not Applicable |