Construct rock reinforced ford in historic creek crossing, for USFS authorized use only, to reduce environmental impacts, stream degradation, and erosion to complete vegetation management activities.
Location
FPNG's Farlow Winter 1/4 Allotment on upper intermittent reaches of East War Creek
Project timeline
1
Scoping Start
08/26/2022
2
Decision
10/2022 (Estimated)
3
Implementation
10/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Rangeland Vegetation Improvements; Watershed Improvements |
| East Branch War Creek Crossing | Decision Signed Date: 10/03/2022 |
| Forests | Nebraska National Forest |
| Districts | Fort Pierre Ranger District |
| Legal Land Description | SE 1/4 S18 T2N R31E |