Issue 3 special use permit amendments to perform shoulder work on Highway 73, which results in the need to move a fiberoptic cable and a water line that serves the Oglala Sioux Tribe.
Location
Highway 73 on National Forest System lands from south of the White River to Kadoka
Project timeline
1
Scoping Start
03/14/2024
2
Decision
07/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 40 Cfr 1506.3(D) |
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| Special Use Permits: Wall Ranger District Highway 73 Improvements | Decision Signed Date: 07/24/2024 |
| Forests | Nebraska National Forest |
| Districts | Wall Ranger District |
| Legal Land Description | Not Applicable |