Replace 14 existing toilets and install one new one with modern facilities.
Location
Campgrounds at Nebraska and Samuel R. McKelvie National Forests and Oglala and Buffalo Gap National Grasslands
Project timeline
1
Scoping Start
04/23/2024
2
Decision
02/2025 (Estimated)
3
Implementation
06/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Replace Fiberglass Vault Toilets | Decision Signed Date: 02/07/2025 |
| Forests | Nebraska National Forest |
| Districts | Nebraska National Forest All Units |
| Legal Land Description | Not Applicable |