This proposal is analyzing the potential for mulching dense pinyon-juniper with a hydroaxe in the San Isabel Creek area north of Crestone CO. Opportunities for public firewood and limited use of prescribed fire will also be examined.
Location
San Isabel Creek
Project timeline
1
Scoping Start
03/01/2009
2
Comment Period
03/01/2009
3
Decision
11/2009 (Estimated)
4
Implementation
07/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements |
| San Isabel Creek Project | Decision Signed Date: 11/09/2009 Legal Notice Date: 11/12/2009 |
| Forests | Rio Grande National Forest |
| Districts | Saguache Ranger District |
| Legal Land Description | San Isabel Creek, Crestone CO |