The proposed project consists of extending a pipeline from an existing water tank to two additional 12%u2019 tire tanks. The majority of the pipeline will be buried where soils and topography allow.
Location
Embargo C&H Allotment
Project timeline
1
Scoping Start
10/01/2014
2
Decision
11/2014 (Estimated)
3
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Chicken Springs Pipeline Extension | Decision Signed Date: 11/17/2014 |
| Forests | Rio Grande National Forest |
| Districts | Divide Ranger District |
| Legal Land Description | Sections 5 and 8, T40N, R4E; NMPM |