Decision Memo Completed

Million Dam spillway improvements

Rio Grande National Forest Rio Grande, Colorado Divide Ranger District

The proposed action is to replace the Million Dam earthen spillway approach section with concrete and then to stabilize the rip rap in the spillway channel

Location

Million Reservoir, approximately 3.5 miles southwest of South Fork, CO.

Project timeline

1
Scoping Start
03/23/2016
2
Decision
06/2017 (Estimated)
3
Implementation
09/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Facility Maintenance
Million Dam spillway improvementsDecision Signed Date: 06/19/2017
ForestsRio Grande National Forest
DistrictsDivide Ranger District
Legal Land DescriptionNot Applicable
Facility management