Decision Memo Completed

Wilber Water Transmission Line Reauthorization

Rio Grande National Forest Rio Grande, Colorado Divide Ranger District

Reauthorization of a spring development and water transmission line per the decree in Division 3 Case No. CA2673 for the Hudson Ditch.

Location

SE1/4 of Sec. 29, T. 40 N., R. 3 E., NMPM, Rio Grande County, Colorado.

Project timeline

1
Scoping Start
02/22/2018
2
Decision
06/2018 (Estimated)
3
Implementation
10/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Wilber Water Transmission Line ReauthorizationDecision Signed Date: 06/29/2018
ForestsRio Grande National Forest
DistrictsDivide Ranger District
Legal Land DescriptionA right-of-way 300 feet in length and 10 feet in width encompassing 0.1 acres more or less in the SE1/4 of Sec. 29, T. 40 N., R. 3 E., NMPM, Rio Grande County, Colorado.