Decision Memo Completed

Double D Stabilization

Shoshone National Forest Park, Wyoming Greybull Ranger District

Stabilization actions on the Double D to mitigate structural hazards at the Double D mine headquarters and Bald Mountain Cabins to maintain historic properties.

Location

Facilities in the area of the Double D Ranch.

Project timeline

1
Scoping Start
01/31/2008
2
Decision
03/2008 (Estimated)
3
Implementation
04/2008 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHeritage Resource Management
Decision Memo Double D Stabilization ProjectDecision Signed Date: 03/06/2008
ForestsShoshone National Forest
DistrictsGreybull Ranger District
Legal Land DescriptionT46N, R103W, Section 21
Heritage resource management