Issue a special use permit to the new owner - terms and conditions would be the same as in the existing permit.
Location
Wind River Ranger District
Project timeline
1
Scoping Start
07/01/2012
2
Comment Period
07/01/2012
3
Decision
02/2013 (Estimated)
4
Implementation
03/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Decision Memo Chamley Outfitter/Guide Business Transfer | Decision Signed Date: 02/26/2013 Legal Notice Date: 02/26/2013 |
| Forests | Shoshone National Forest |
| Districts | Wind River Ranger District |