Project timeline
1
Scoping Start
03/12/2014
2
Decision
04/2014 (Estimated)
3
Implementation
05/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shoshone National Forest |
| Districts | Wind River Ranger District |
| Legal Land Description | Not Applicable |