Proposal for integrated project to improve riparian conditions and administrative site management along the Wapiti Ranger Station, North Fork of the Shoshone River, South Fork of the Shoshone River, and East Painter Creek.
Location
Area running from the Big Game Campground west to the Wapiti Campground, encompassing a portion of the Elk Fork and Sweetwater creeks, area along South Fork Shoshone River, and East Fork Painter Creek
Project timeline
1
Scoping Start
01/31/2023
2
Decision
07/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19); 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Rangeland Vegetation Improvements; Watershed Improvements |
| 2023 Stream Restoration, Flood Resilience, & Habitat Improvement | Decision Signed Date: 07/25/2023 |
| Forests | Shoshone National Forest |
| Districts | Wapiti Ranger District |
| Legal Land Description | Wapiti Ranger Station: Sections 15, 16, 21 & 22, T52N R106W; South Fork Work Center: Section 04, T48N R106W; East Fork Painter Creek: Section 06, T55N R105W |