High Plains Power, Inc. proposes to replace and bury approximately 15 miles of existing primary overhead power lines. The power lines service inholdings located in the Horse Creek area of the Wind River District of the Shoshone National Forest.
Location
Horse Creek Road Area
Project timeline
1
Scoping Start
11/07/2024
2
Decision
12/2024 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| Horse Creek Power Line Burial | Decision Signed Date: 12/05/2024 |
| Forests | Shoshone National Forest |
| Districts | Wind River Ranger District |
| Legal Land Description | T43N R107W Sections 24 and 25, T43N R106W Sections 3, 9, 10, 16, 19, 20, and 21 |