Project will include initial exploration and potential development of up to 52 wells directionally drilled from up to 7 well pads in the Alkali Creek/Bear Gulch area. Project includes new road building and pipeline installation in the road corridor.
Location
The project area is about 16 miles south of Silt, Colorado
Project timeline
1
Scoping Start
02/21/2006
2
Comment Period
01/29/2007
3
Decision
05/2008 (Estimated)
4
Implementation
07/2008 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Plains Exploration and Production Company, Hell | Decision Signed Date: 05/02/2008 Legal Notice Date: 05/07/2008 |
| Forests | White River National Forest |
| Districts | West Zone/Rifle Ranger District |
| Legal Land Description | T8S, R92W, Sections 23, 24, 25 and 26 |