Project timeline

1
Scoping Start
10/30/2012
2
Comment Period
10/30/2012
3
Decision
11/2013 (Estimated)
4
Implementation
06/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Watershed Improvements
Golden Horseshoe Trail constructionDecision Signed Date: 11/01/2013
ForestsWhite River National Forest
DistrictsEast Zone/Dillon Ranger District
Legal Land DescriptionNot Applicable
Wildlife, fish, rare plantsWatershed managementRecreation managementRoad management