Mosquito control using a natural bacterial byproduct, "Bti" on areas east of Aspen near Wildwood School & Difficult CG. Less than 5 acres of wetland areas to be controlled on an as-needed basis. Treatment is by hand, after assessment is completed.
Location
Scattered patches of FS lands east of Aspen along the roaring Fork River.
Project timeline
1
Scoping Start
06/30/2010
2
Comment Period
04/18/2013
3
Objection Period Start
03/23/2015
4
Decision
05/2015 (Estimated)
5
Implementation
05/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Mosquito Abatement DNFONSI | Decision Signed Date: 05/15/2015 |
| Forests | White River National Forest |
| Districts | West Zone/Aspen Ranger District |
| Legal Land Description | 6th P.M., T. 10 S., R. 84 W., Sections 28, 33, and 34 |