Reissuance of transmission line permits to PSCo that have expired: Hopkins/Leadville Line, Wolcott-Avon-Vail line, and the Wolcott to Beaver Creek line.
Location
Various locations on the White River
Project timeline
1
Scoping Start
11/20/2012
2
Decision
09/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | White River National Forest |
| Districts | West Zone/Sopris Ranger District; East Zone/Eagle Ranger District; East Zone/Holy Cross Ranger District; West Zone/Rifle Ranger District |
| Legal Land Description | Not Applicable |