Allow unlicensed OHVs on certain segments of the open road system on Eagle/Holy Cross Ranger Districts
Location
Eagle/Holy Cross RD
Project timeline
1
Scoping Start
06/27/2013
2
Comment Period
07/01/2013
3
Objection Period Start
03/13/2014
4
Decision
05/2014 (Estimated)
5
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Travel Management |
| Eagle/Holy Cross 2013 Motor Vehicle Use Map Update | Decision Signed Date: 05/15/2014 |
| Forests | White River National Forest |
| Districts | East Zone/Eagle Ranger District; East Zone/Holy Cross Ranger District |
| Legal Land Description | Not Applicable |