New authorization for construction of a cellular phone comm site along I-70 between the Eisenhower Tunnel & East Dillon. The facility will be a multi-carrier facility consisting of one prefab equip shelter and 2 towers.
Location
5 miles east of Silverthorne on I-70 at mile marker 211 on the south side of the highway. Site is within the highway right-of-way.
Project timeline
1
Scoping Start
04/01/2013
2
Decision
10/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | White River National Forest |
| Districts | East Zone/Dillon Ranger District |
| Legal Land Description | Section 25, T. 4 S., R. 77 W., 6th P.M. |