Environmental Assessment Cancelled

American Tower- A-Basin Communications Site

White River National Forest Summit, Colorado East Zone/Dillon Ranger District

New authorization for construction of cellular phone comm site along US Highway 6 between Loveland Pass and Keystone (A-Basin). The facility will be multi-carrier facility consisting of one prefabricated equipment shelter and two towers.

Location

Adjacent to US Highway 6 right-of-way immediately south and east of A-Basin Ski Area.

Project timeline

1
Scoping Start
07/2014 (Estimated)
2
Comment Period
07/2014 (Estimated)
3
Objection Period Start
08/2014 (Estimated)
4
Decision
10/2014 (Estimated)
5
Implementation
10/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsWhite River National Forest
DistrictsEast Zone/Dillon Ranger District
Legal Land DescriptionSection 2, T. 5 S., R. 76 W., 6th P.M.
Special use management