The project would be located along Turkey Creek and Gypsum Creek. Turkey Creek parallells Forest Service Road 709 (Shrine Pass). Gypsum Creek parallels Forest Service Road 412 (Gypsum Creek Road).

Project timeline

1
Scoping Start
05/2014 (Estimated)
2
Decision
06/2014 (Estimated)
3
Implementation
07/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Watershed Improvements
ForestsWhite River National Forest
DistrictsEast Zone/Holy Cross Ranger District
Legal Land DescriptionTurkey Creek- T 6S, R 80W, Sect. 1, 10, 11, 15, 16 Gypsum Creek- T 6S, R 85 W, and Sect. 32, 33, 34, 35
Recreation managementWatershed management