Construct 650 feet of new road and obliterate/rehabilitate section of FSR 250 damaged by ditch overflow in spring 2014. Install a culvert where Coal Creek Feeder ditch crosses east end of re-route.
Location
Approximately 1.1 miles east of Elbow Park (intersection of FSR 250 and 258)
Project timeline
1
Scoping Start
06/23/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Forest Service Road 250 Road Realignment | Decision Signed Date: 07/14/2014 |
| Forests | White River National Forest |
| Districts | West Zone/Blanco Ranger District |
| Legal Land Description | T2N, R91W, Sec 27 |