The concern for future debris flows at Redstone Campground area has initiated the Forest Service to review, analyze, and propose actions to provide camper safety and a debris management plan to minimize sediment into the Crystal River.
Location
Redstone Campground adjacent to Colo Hwy 133 Crystal River
Project timeline
1
Scoping Start
04/2016 (Estimated)
2
Comment Period
04/2016 (Estimated)
3
Objection Period Start
10/2016 (Estimated)
4
Decision
11/2016 (Estimated)
5
Implementation
11/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Road Improvements/Construction; Watershed Improvements |
| Forests | White River National Forest |
| Districts | West Zone/Sopris Ranger District |
| Legal Land Description | 39 18%u2019 09%u201D N %u2013 107 06%u2019 57%u201D W |