Project timeline
1
Scoping Start
03/18/2016
2
Decision
05/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Vail Summer Construction 2016 CE | Decision Signed Date: 05/06/2016 |