Proposal to maintain grid reliability by replacing five overhead electric transmission structures and the installation of two new mid-span structures along PSCo line 3014, a 138 kV transmission line linking the Ute Rifle and Collbran Substations.
Location
The Ute Rifle to Collbran Transmission line runs along Silt/Collbran road south of Silt, Colorado.
Project timeline
1
Scoping Start
10/04/2016
2
Decision
04/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Xcel Energy Line Capacity Project - Ute Rife to Collbran Line 3014 | Decision Signed Date: 04/16/2018 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests; White River National Forest |
| Districts | Grand Valley Ranger District; West Zone/Rifle Ranger District |
| Legal Land Description | Secs. 27, 28, 31, 32, and 33, T8S-R92W, 6thPM, Mesa County, Colorado |