The following are proposed on USFS lands: approximately 60 acres cleared trail and gladed terrain; chairlift and ancillary infrastructure; bottom terminal access road; and 50 acres snowmaking, pump station, 18,000 feet line, and two storage ponds.
Location
White River National Forest, Aspen - Sopris Ranger District, Aspen Mtn. Ski Area special use permit area
Project timeline
1
Scoping Start
05/16/2018
2
Comment Period
05/16/2018
3
Objection Period Start
11/28/2018
4
Decision
03/2019 (Estimated)
5
Implementation
03/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Aspen Mountain Pandora Development and Summit Snowmaking Projects | Decision Signed Date: 03/20/2019 |
| Forests | White River National Forest |
| Districts | West Zone/Aspen Ranger District |
| Legal Land Description | T10S R84W S30 |