Provide additional snowmaking coverage on 33 acres of terrain in the Alpine Springs area and add a storage structure and tubing hill operations kiosk in the Elk Camp Meadows area.
Location
Within the Snowmass Ski Area
Project timeline
1
Scoping Start
08/23/2018
2
Comment Period
08/23/2018
3
Objection Period Start
12/17/2018
4
Decision
02/2019 (Estimated)
5
Implementation
05/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Snowmass Snowmaking and Elk Camp Meadows Projects | Decision Signed Date: 02/22/2019 |
| Forests | White River National Forest |
| Districts | West Zone/Aspen Ranger District |
| Legal Land Description | Not Applicable |