Sunlight Mountain Resort is proposing to install a new chairlift, construct a pit toilet and enhance trail improvements at Sunlight Mountain Resort (SMR).
Location
Sunlight Mountain Resort: T7S; R 89W; Section 33
Project timeline
1
Scoping Start
01/23/2020
2
Decision
11/2020 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Sunlight Mountain Resort East Ridge Chairlift Installation | Decision Signed Date: 11/10/2020 |
| Forests | White River National Forest |
| Districts | West Zone/Sopris Ranger District |
| Legal Land Description | Not Applicable |