Construction, operation and maintenance of a fiber optic telecommunication line including 1.51 miles of underground cable and 560 feet of overhead cable on an existing electric distribution line right-of-way north of Green Mountain Reservoir
Location
Existing electric power line along Heeney Road (Summit County Road 30) & north of Green Mountain Reservoir Dam
Project timeline
1
Scoping Start
02/28/2018
2
Decision
05/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Mountain Parks Electric, INC-Fiber Optic Line | Decision Signed Date: 05/12/2020 |
| Forests | White River National Forest |
| Districts | White River National Forest All Units |
| Legal Land Description | Sections 11, 14 and 15, Township 2 South, Range 80 West, 6th PM, Summit County, CO |