Re-issuance of an existing authorization for variable kV electrical distribution lines and fiber optic cable.
Location
General area of permit reauthorization is north end of Summit County
Project timeline
1
Scoping Start
07/30/2020
2
Decision
01/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Reissuance of Mountain Parks Electric, Inc Special Use Permit | Decision Signed Date: 01/12/2021 |
| Forests | White River National Forest |
| Districts | East Zone/Dillon Ranger District |
| Legal Land Description | Sec 11, 13, 14, 15, 35, 36 of T2S, R80W; Sec 34 T2S, R79W; Sec 18, 28, 29, 33 of T3S, R78W; Sec 2, 3 T3S, R79W: 6th Principal Meridian |