Decision Memo Completed

Mountain Parks Electric, Inc Permit Renewal

White River National Forest Summit, Colorado East Zone/Dillon Ranger District

Re-issuance of an existing authorization for variable kV electrical distribution lines and fiber optic cable.

Location

General area of permit reauthorization is north end of Summit County

Project timeline

1
Scoping Start
07/30/2020
2
Decision
01/2021 (Estimated)
3
Implementation
06/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Reissuance of Mountain Parks Electric, Inc Special Use PermitDecision Signed Date: 01/12/2021
ForestsWhite River National Forest
DistrictsEast Zone/Dillon Ranger District
Legal Land DescriptionSec 11, 13, 14, 15, 35, 36 of T2S, R80W; Sec 34 T2S, R79W; Sec 18, 28, 29, 33 of T3S, R78W; Sec 2, 3 T3S, R79W: 6th Principal Meridian
Special use management