Decision Memo Completed

Amend PSCo (XCEL) Permit DIL796 to replace failing structures 63 and 85

White River National Forest Summit, Colorado East Zone/Dillon Ranger District

PSCo transmission line 9188 needs to replace 2 failing structures and addition of weights to 1 structure in order to correct identified deficiencies.

Location

Dillon Ranger District, PSCo (XCEL) powerline "Dillon-Robinson 115kV Line".

Project timeline

1
Scoping Start
05/17/2021
2
Decision
07/2021 (Estimated)
3
Implementation
07/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Amend PSCo (XCEL) Permit DIL796 to replace failing structures 63 and 8Decision Signed Date: 07/17/2021
ForestsWhite River National Forest
DistrictsEast Zone/Dillon Ranger District
Legal Land DescriptionLine 9188 - Structure 63 / 39.489913 -106.136833 / 6S 78W 32 Line 9188 - Structure 85 / 39.459798 -106.13945 / 7S 78W 8 Line 9188 - Structure 86 / 39.458515 -106.141104 / 7S 78W 8
Special use management