Xcel Energy has proposed to replace a bridge over Gypsum Creek at the Cottonwood-Gypsum Creek Rd intersection to accommodate maintenance vehicle weight. This non-Forest System Road provides access to Xcel Transmission Lines and private land.
Location
NE1/4, NE1/4, Sec 16, 6S, 85W, 6th PM
Project timeline
1
Scoping Start
10/27/2021
2
Decision
10/2022 (Estimated)
3
Implementation
10/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance |
| Gypsum Creek Bridge Replacement | Decision Signed Date: 10/19/2022 |
| Forests | White River National Forest |
| Districts | East Zone/Holy Cross Ranger District |
| Legal Land Description | Not Applicable |