Special use permit for the installation of fiber optic line and conduit along an existing overhead utility right-of-way from the intersection of State Highway 133 and Gunnison County Rd 3 to the Forest boundary at the Darien parcel in Marble.
Location
Intersecton of CSH-133 and Gunnison County Rd 3 through NFS lands to the Darien parcel (east side of Crystal River).
Project timeline
1
Scoping Start
11/10/2021
2
Decision
05/2022 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Visionary Broadband Fiber Optic Install CSH133 to Darien | Decision Signed Date: 05/31/2022 |
| Forests | White River National Forest |
| Districts | West Zone/Aspen Ranger District |
| Legal Land Description | Not Applicable |