Amending the existing PSCo permit#DIL462 to add 1,500 ft of existing gas line that was inadvertently deleted in 2001. In addition, a 6 inch steel main gas line would be installed to reinforce the existing line on approx.1500 ft of National Forest.
Location
Keystone area just west of the Landfill Road.
Project timeline
1
Scoping Start
08/21/2023
2
Decision
09/2024 (Estimated)
3
Implementation
10/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PSCo Keystone Resort Steel Main Gasline Reinforcement | Decision Signed Date: 09/12/2024 |
| Forests | White River National Forest |
| Districts | East Zone/Dillon Ranger District |
| Legal Land Description | Township 5 South, Range 77 West, Section 22, 6th P.M. |