Plan of Operations Review for the Double Eaton Mine. Mineral material will be excavated by hand and processed on site using a trowel and sluice box. Access to the mine will be by non-motorized means. No structures. Operations would be up to 2 mon/yr.
Location
Approximately 5 miles northwest of Fulford, Colorado.
Project timeline
1
Scoping Start
10/28/2022
2
Decision
04/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | White River National Forest |
| Districts | East Zone/Holy Cross Ranger District |
| Legal Land Description | Legal location: W 1/2, NE 1/2, SE1/4,of Section 6, Township 6S, Range 83W of the 6th meridian |