Construction of an approximate 1.6-mile non-motorized trail to extend the existing Eagle-Vail Trail # 2351, with 0.27 miles on National Forest Land. Additionally, 0.25 miles of social trail will be decommissioned and permit #HOL937 will be amended.
Location
Project is located south of Highway 6 adjacent to the Eagle-Vail Metro district in Section 18 Township 5 South, Range 81 West 6th Principal Meridian
Project timeline
1
Scoping Start
03/27/2024
2
Decision
08/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Trail Management |
| Extension of Eagle-Vail Trail #2351 | Decision Signed Date: 08/12/2024 |
| Forests | White River National Forest |
| Districts | East Zone/Holy Cross Ranger District |
| Legal Land Description | Not Applicable |