Install approximately 830 yards of underground powerline to improve snowmaking capability at the existing Downtown Ski Trail.
Location
Located within the Red River Ski Area permit boundary, near the Town of Red River, Taos County New Mexico
Project timeline
1
Scoping Start
05/02/2012
2
Comment Period
05/03/2012
3
Decision
07/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Red River Ski Area Downtown Race Hill Snowmaking Power Line Project | Decision Signed Date: 07/26/2012 Legal Notice Date: 08/02/2012 |
| Forests | Carson National Forest |
| Districts | Questa Ranger District |
| Legal Land Description | T. 29N, R. 14E, Section 35 |